Thursday, December 21, 2006

Ready for delivery


All of our foundation work has been completed. We are approaching Christmas so we have a delay in getting our house package delivered. We are scheduled for January 15th and 16th for delivery of our wall and roof system. We will have the windows already installed in the walls but chose to construct our floor system locally. We had the option of purchasing our exterior doors and having them delivered but chose a local option on that as well. Our lot required a crawl space and cost a little more than I anticipated because of the slope. We will have 5-6 steps up to our front porch where I thought there would probably be 3-4. Concrete and block are more expensive these days than you might imagine!
At this point we are shopping siding, shutters, brick, shingles, garage door, and thinking of how our interior stairway should look.