Day - 3 - 2nd story floor system, 1st story framing


Today the 2nd story floor joists and 1st story interior framing were worked on. Tomorrow the 2nd floor sheeting, stairway, and additional interior framing will be done along with finishing the exterior walls of the garage. On the front of the house two sections with windows had to be adjusted to level. Windows and exterior cdx had to be removed from both in order to get the level correct