The HVAC contractor will be finishing up with rough-in by Friday.
The electricians are working on our job after their regular hours so that will take a little longer. David has a baby coming in about a week so I know he has probably more pressure on him than getting wiring done right now. I talked to him Monday and he said they would be done by the 1st of the month.
We need to get the plumber started by Monday and he will be working about three days on site.
Our roofer got the flu so his plans to be finishing this past Monday fell through.
Our plan is to be working on insulation by the 1st of March and be ready for sheetrock before the 8th.
We are having more Spring-like weather this week so it may be time to get the brick out to the site. We had a few weeks that were too cold for mortar and we have held off on the brick until consistent warmer weather holds up. This week is consistent temps in the 50s.
Wednesday, February 21, 2007