This weekend we worked on nailing in blocking in closets and the kitchen so shelving and cabinets will have something to better hang onto. We are ready to begin putting in insulation and sheetrock right away. The electrical work is ready for the rough-in inspection and the plumber should be done by Tues. At least we can get started on the areas where there is no plumbing if we need to. The A/C rough-in is complete except for a couple small items.
We will probably get our brick delivered this week and possibly the siding. We will do the siding first and then have the mason come in at least after we have put up the bottom levels of siding around the house. When we do the interior work we plan to do the house room by room putting in insulation, hanging sheetrock, and then mudding.
The weather has been great, high 60s to 70 lately. We are looking forward to getting some serious progress underway.